International projects: Project «Reconstruction of the heat supply system of city district Kyivska Str. – Talalihina from the boiler house on P. Komuny Str, 18 in Vinnytsia» (cooperation on raising NEFCO funds within DemoUkrainaDH Programme)
Manage PermissionsManage Permissions

Project «Reconstruction of the heat supply system of  city district Kyivska Str. – Talalihina from the boiler house on  P. Komuny Str, 18 in Vinnytsia»  (cooperation on raising NEFCO funds within DemoUkrainaDH  Programme)

1.jpgProject duration:  2014

Project budget: 937 000 euro (300 000 euro – grant from NEFCO, 400 000  euro – loan from NEFCO, 237 000  euro – money of Vinnytsia MTE)

Within the project the following activities are foreseen:

-          closing ineffective boiler on Kyivska str., 82  and connecting consumers to the boiler house on  P. Komuny  str., 18;

-          reconstruction  of 1.4 km of heating networks  and  replacement with  pre-insulated pipes;

-          reconstruction of Central heat supply station  (CHS) on the Griboyedova Str. , 3 and implementation of 12 individual heat supply stations (HIS);

connecting the boiler equipment, CHSs and IHSs to SCADA system.